港口航道与近海工程2025,Vol.62Issue(3):108-111,4.DOI:10.16403/j.cnki.ggjs20250325
围埝合拢口和吹填造陆逆序施工的方法
Construction of Cofferdam Closure Gap and Sea Reclamation in Reverse Order
王桂松 1李阳光 1陈玉华1
作者信息
- 1. 中交第一航务工程勘察设计院有限公司,天津 300220
- 折叠
摘要
Abstract
As an inevitable technical problem,the cofferdam closure gap is more difficult to be closed by adopting the traditional construction process of sea reclamation,larger cofferdam area leads to more severe problem.Based on the traditional construction process,the closure gap shall be closed before sea reclamation,which prevents ocean from pollution,but results in a huge impact on the cofferdam closure gap under internal/external water flow pressure.The above construction requires the optimum combination of time,place and staff,is characterized with low efficiency and high failure ratio.In the case,the construction process was improved by setting up multi-level anti-fouling curtains combined with sea reclamation and cofferdam construction.The new measure reduced internal/external water flow pressure while closing the gap,and basically decreased the difficulty in closing the gap.关键词
陆域吹填/防污帘/合龙/水流压力Key words
sea reclamation/anti-fouling curtain/closure gap/water flow pressure分类
交通工程引用本文复制引用
王桂松,李阳光,陈玉华..围埝合拢口和吹填造陆逆序施工的方法[J].港口航道与近海工程,2025,62(3):108-111,4.