煤气与热力2025,Vol.45Issue(5):80-83,4.
LNG接收站长距离大尺寸管道预冷模拟分析
Simulation Analysis of Pre-cooling of Long-distance and Large-size Pipelines in LNG Terminal
孔奇栋 1张强强 1冯建周 1宋珺霆 1田雨阳1
作者信息
- 1. 海洋石油工程股份有限公司,天津 300461
- 折叠
摘要
Abstract
During the commissioning of LNG terminal,in order to avoid the stress damagecaused by LNG en-tering the pipeline directly,it is necessary to pre-cool the pipeline with low temperature nitrogen.Based on the pre-cooling problem of the unloading pipeline at a LNG terminal,the pre-cooling method of"low-temperature nitrogen pre-cooling and low-temperature liquid nitrogen spraying"is adopted to simulate the temperature change during the pre-cooling process with the help of the ANSYS Fluent software discrete phase model.Adding liquid nitrogen spraying along the pipeline can effectively reduce the temperature of nitrogen gas to meet the pre-cooling requirements of long-distance pipelines.The larger the liquid nitrogen spraying volume,the lower the outlet temperature of the pipeline,and the better the pre cooling effect of the pipeline.for the pre-cooling of large-size and long-distance pipelines,the pre-cooling of pipelines by add-ing liquid nitrogen spraying ports along the pipeline can meet the requirements of pre-cooling of the pipe-line.关键词
LNG接收站/管道预冷/数值模拟/液氮喷淋Key words
LNG terminal/pipeline pre-cooling/nu-merical simulation/liquid nitrogen spraying分类
能源科技引用本文复制引用
孔奇栋,张强强,冯建周,宋珺霆,田雨阳..LNG接收站长距离大尺寸管道预冷模拟分析[J].煤气与热力,2025,45(5):80-83,4.