水电站机电技术2025,Vol.48Issue(6):1-7,40,8.DOI:10.13599/j.cnki.11-5130.2025.06.001
某大型抽水蓄能电站进相运行能力分析与试验
Analysis and test of the leading phase operation capacity of a large pumped storage power station
蔡晨昕 1吴军锋 1韦志付 1王嘉鑫 1贝心志1
作者信息
- 1. 华东天荒坪抽水蓄能有限责任公司,浙江安吉 313302
- 折叠
摘要
Abstract
In order to alleviate excess reactive power caused by the low load period of the power grid system,it is necessary to adjust the pumped storage units to leading phase operation,thus adjusting the system voltage.This paper briefly introduces the basic principles of leading phase operation of pump-hydro-generators,analyzes the various limiting factors of leading phase operation,and calculates the various parameter limits of leading phase operation based on the actual working conditions of units in a large pumped storage power station in China.This paper determines the test plan,and finally determines the leading phase operation capacity of the pumped storage units through field leading phase operation tests,providing a scientific basis for the leading phase operation of pumped storage units.关键词
抽水蓄能/进相运行/无功功率Key words
pumped storage/leading phase operation/reactive power分类
建筑与水利引用本文复制引用
蔡晨昕,吴军锋,韦志付,王嘉鑫,贝心志..某大型抽水蓄能电站进相运行能力分析与试验[J].水电站机电技术,2025,48(6):1-7,40,8.