| 注册
首页|期刊导航|化工矿产地质|长春某深基坑冠梁变形突变原因及处理措施分析

长春某深基坑冠梁变形突变原因及处理措施分析

吴丽萍 周碧池 霍庆明 徐斌

化工矿产地质2025,Vol.47Issue(2):168-174,7.
化工矿产地质2025,Vol.47Issue(2):168-174,7.

长春某深基坑冠梁变形突变原因及处理措施分析

Analysis of the Causes of Sudden Deformation of the Capping Beam in a Deep Foundation Pit in Changchun and Treatment Measures

吴丽萍 1周碧池 1霍庆明 2徐斌2

作者信息

  • 1. 长春工程学院勘查与测绘工程学院,吉林 长春 130000
  • 2. 中国建筑一局(集团)有限公司,吉林 长春 130000
  • 折叠

摘要

Abstract

With a deep foundation pit support project in Changchun City as the research backdrop,this paper analyzes the causes of the sudden deformation of the capping beam on the north side of the foundation pit and proposes reasonable treatment measures.The analysis shows that the main cause of the capping beam's sudden change is that during the excavation of the sump well at the base of the foundation pit,heavy rainfall caused the bottom of the foundation pit to be soaked by rainwater,and the rainwater seeped into the ground through cracks on the surface,resulting in a decrease in the strength of the soil layers both inside and outside the foundation pit,etc.;the secondary causes include a large amount of groundwater,problems such as the construction of anchor cables and uneven force on the piles.This study integrates the finite element numerical simulation with the actual monitoring data and conducts a comparative analysis.This study also proposes setting up four anchorages at the deformed part of the capping beam,and evaluates the treatment effect.The results show that this measure can effectively control the further deformation of the capping beam,providing reference experience for other similar foundation pit projects.

关键词

冠梁变形/有限元软件/对比分析/锚碇

Key words

Capping beam deformation/Finite element software/Comparative analysis/Anchorage