漂卵石河道桥梁中墩钢管桩旋喷组合加固施工技术

Construction Technology for Combined Reinforcement with Steel Pipe Piles and Jet Grouting for Middle Piers of Bridges in Boulder-Strewn River Channels

巫德武 1苏小明 1罗贵 1朱军1

作者信息

  • 1. 中国水利水电第十工程局有限公司,四川 成都 610036
  • 折叠

摘要

Abstract

The formation structure of the boulder-strewn river is loose,the voidage is large,and the permeability is strong,and the reinforcement effect is poor because of the slurry stringing and leakage in the rotary jet rein-forcement.Seepage control walls,due to their excessive occupation of the river channel during construction,long construction period,and high cost,are not suitable for all foundation reinforcement projects in boulder-strewn river channels.Through describing the construction technology for combined reinforcement with steel pipe piles and jet grouting used for middle piers of Jinlong Dadu River Bridge,this paper puts forward solutions and methods for a series of challenges in foundation reinforcement construction of boulder-strewn river chan-nels,such as pipe sinking,hole deviation control,hole leakage,schedule control and cost control,and imple-ments these measures,achieving good results.

关键词

漂卵石河道/基础加固/钢管桩旋喷组合加固/施工技术/金龙大渡河大桥

Key words

boulder-strewn river/foundation reinforcement/combined reinforcement with steel pipe piles and jet grouting/construction technology/Jinlong Dadu River Bridge