Abstract
This paper provides an in-depth exploration of the key technologies and methodologies for headrace tunnel construction in hydropower projects.Through detailed analysis of engineering geological survey,con-struction key points,shaft construction,measurement,and advanced geological prediction methods,the study aims to deliver scientific and systematic construction guidance for related projects,ensuring engineering quality and safety.关键词
水电站/引水隧洞/施工技术Key words
hydropower project/headrace tunnel/construction technology分类
建筑与水利引用本文复制引用