Abstract
In the construction of anchor channel concrete for water resources allocation project in the Pearl River Delta,the traditional curing technology faces the challenge of long time and low efficiency.This paper puts for-ward the application of rapid curing technology,by adding the appropriate proportion of rapid curing agent to the concrete,the initial setting can be achieved in 1 to 2 hours,and the complete curing in 3 to 4 hours.The re-sults show that the construction efficiency is significantly improved,and the compressive strength can reach 30MPa within 24 hours,shortening the construction period and reducing the environmental impact.This tech-nology improves concrete fluidity,reduces shrinkage rate,reduces crack risk,ensures construction quality,and provides an efficient solution for foundation treatment.关键词
快速固化技术/锚具槽混凝土施工/施工效率/环境影响Key words
rapid curing technology/concrete construction with anchor groove/construction efficiency/environ-mental impact分类
核科学