富水地层暗挖地铁车站施工竖井超高压旋喷桩止水试验研究

宋扬 郑昊 杨航 王凯

市政技术2025,Vol.43Issue(7):162-169,178,9.
市政技术2025,Vol.43Issue(7):162-169,178,9.DOI:10.19922/j.1009-7767.2025.07.162

富水地层暗挖地铁车站施工竖井超高压旋喷桩止水试验研究

Study on Waterproof Test of Ultra-high Pressure Rotary-jet Grouting Pile for the Shaft of Subway Station in Water-rich Stratum

宋扬 1郑昊 2杨航 3王凯3

作者信息

  • 1. 北京市政路桥管理养护集团有限公司,北京 100097
  • 2. 北京市政建设集团有限责任公司,北京 100089
  • 3. 北京交通大学,北京 100044
  • 折叠

摘要

Abstract

In order to study the waterproof effect of ultra-high pressure rotary-jet grouting piles for underground ex-cavation subway station in the water-rich stratum,the No.3 shaft of Shifoying Metro Station of Beijing Metro Line 3 was taken as an example to carry out the waterproof test research of ultra-high pressure rotary-jet grouting piles.First,the experimental research on the proportion of the jet grouting liquid was carried out to develop high-strength and high impermeability grouting materials;Then,the on-site waterproof test of the jet grouting pile was conducted.The effect of waterproof by the rotary-jet grouting piles was analyzed by the microstructure changes before and after the grouting of the soil,the physical mechanical test of the rotary-jet grouting pile and the effect of waterproof by completed piles.The research results show that the soil sample changes from a loose structure to a compact structure after the rotary-jet grouting and significantly enhanced integrity of the soil;Both the compressive strength and im-permeability of the reinforced materials are greatly improved;The measured verticality of the rotary-jet grouting test pile is 0.1‰~2.5‰,which meets the design requirements of verticality not greater than 5‰ in the engineering de-sign.The ultra-high pressure rotary-jet grouting pile has a good waterproof effect in the shaft,and basically cuts off the hydraulic connection between the inside and outside of the shaft.The experimental results provide a basis for the design of ultra-high pressure rotary-jet grouting waterproof scheme for underground excavation stations.

关键词

富水地层/竖井/超高压旋喷桩/注浆材料配比/强度/渗透性/止水效果

Key words

water-rich stratum/shaft/ultra-high pressure rotary-jet grouting pile/mixing ratio of grouting materi-als/strength/permeability/waterproof effect

分类

建筑与水利

引用本文复制引用

宋扬,郑昊,杨航,王凯..富水地层暗挖地铁车站施工竖井超高压旋喷桩止水试验研究[J].市政技术,2025,43(7):162-169,178,9.