太阳能Issue(8):39-44,6.DOI:10.19911/j.1003-0417.tyn20240923.02
机场净空高度对塔式太阳能热发电站选址布局的影响
IMPACT OF AIRPORT OBSTACLE-CLEARANCE ALTITUDE ON SITE SELECTION AND LAYOUT OF TOWER CSP STATION
俞昊 1杨都堂 1桂鹏1
作者信息
- 1. 浙江可胜技术股份有限公司,杭州 310000
- 折叠
摘要
Abstract
Among the mainstream CSP technology route,the tower technology route offers prominent advantages in investment cost and techno-economic performance,positioning it as China,most competitive,and most mature CSP technology route.However,airport obstacle-clearance protection requirements restrict site selection for tower CSP stations in certain regions.This paper provides a detailed study of the requirements for the establishment and review of airport obstacle-clearance protection areas in relevant documents,clarifies the specific division of airport obstacle-clearance protection areas and their limitations on the site selection of tower CSP stations,and determines the site selection range of tower CSP stations within the airport obstacle-clearanc protection area.The research results show that it is recommended to construct small tower CSP stations with heat absorption tower height less than 150 m within the obstacle limit surface zone.Tower CSP stations with a heat absorption tower height of 150~200 m can be constructed within 10 km on both sides of the centerline of the airport runway,within 20 km outside the runway end,and outside the obstacle limit surface,the specific approval documents from relevant departments shall prevail.In other areas within a horizontal radius of 55 km centered on the airport reference point,the height of the heat absorption tower is not limited.关键词
机场净空/塔式太阳能热发电站/吸热塔/选址布局Key words
airport obstacle-clearance/tower CSP station/heat absorption tower/site selection and layout分类
能源科技引用本文复制引用
俞昊,杨都堂,桂鹏..机场净空高度对塔式太阳能热发电站选址布局的影响[J].太阳能,2025,(8):39-44,6.