长距离引水隧洞竖井信息化施工关键技术研究

董楠楠

安徽地质2025,Vol.35Issue(3):233-236,4.
安徽地质2025,Vol.35Issue(3):233-236,4.

长距离引水隧洞竖井信息化施工关键技术研究

Research on key informatization technologies for construction of vertical shaft of long-distance water diversion tunnel

董楠楠1

作者信息

  • 1. 安徽省地质矿产勘查局313地质队,安徽 六安 237010
  • 折叠

摘要

Abstract

Currently,safety risks in long-distance water diversion tunnel construction lead to inefficient schedule control and resource wastage.This study examines the Xianglushan deep-buried tunnel as a case study to explore key informatization technologies for vertical shaft construction.Through geological monitoring and digital surveying,monitoring nodes are deployed across the construction zone,enabling 3D tunnel modeling for real-time geological assessment and risk early-warning.The implemented construction information management system visualizes operational parameters,optimizes construction sequencing,and rationalizes material allocation,thereby enhancing excavation progress while minimizing resource consumption.Field results demonstrate that the integrated geological monitoring and information management system significantly improves construction efficiency and achieves balanced resource utilization.

关键词

长距离引水隧洞/隧洞竖井/竖井开挖/地质监测/信息化

Key words

long-distance water diversion tunnel/vertical shaft of tunnel/vertical shaft excavation/geological monitoring/informatization