| 注册
首页|期刊导航|路基工程|基于折减系数的全风化花岗岩边坡稳定性评价

基于折减系数的全风化花岗岩边坡稳定性评价

杨波 南宁 康领 孙建仁 王博 赵亚婉

路基工程Issue(5):37-44,8.
路基工程Issue(5):37-44,8.DOI:10.13379/j.issn.1003-8825.202404049

基于折减系数的全风化花岗岩边坡稳定性评价

Evaluation of Completely Weathered Granite Slope Stability Based on Reduction Coefficient

杨波 1南宁 2康领 1孙建仁 3王博 2赵亚婉2

作者信息

  • 1. 新疆生产建设兵团建设工程(集团)有限责任公司,乌鲁木齐 830002
  • 2. 中交第一公路勘察设计研究院有限公司,西安 710075
  • 3. 新建生产建设兵团第七师奎屯河引水工程建设管理局,新疆奎屯 833200
  • 折叠

摘要

Abstract

The physical and mechanical parameters of rock and soil were obtained from two typical disease slopes of fully weathered granite selected in a highway through in-situ test and indoor test.The average reduction coefficient was calculated,and the slope stability simulation was carried out.The classification method of stability evaluation and the focus of slope maintenance were put forward.The result shows that,the fully weathered granite slope collapse is still one of the main diseases in the operation period;the simulation calculation parameters should be based on the field test,because the indoor test value is a little small.Based on the method of reducing geotechnical parameters,the slope stability of the study section can be divided into Ⅰ,Ⅱ,Ⅲ and Ⅳ categories.The slope stability is closely related to the thickness of fully weathered granite,slope rate and wide platform.Class Ⅰ slope should focus on daily maintenance.Class Ⅱ slope should rely on the development of slope deformation and slope toe seepage.Class Ⅲ slope should be monitored for stability.If obvious signs of deformation are found,special survey and design of slope should be carried out in time.Class Ⅳ slope should have special assessment,survey and design of slope conducted.

关键词

运营公路/全风化花岗岩/病害边坡/稳定性评价/养护

Key words

highwayinoperationperiod/completelyweatheredgranite/disease-infectedslope/stabilityevaluation/maintenance

分类

交通工程

引用本文复制引用

杨波,南宁,康领,孙建仁,王博,赵亚婉..基于折减系数的全风化花岗岩边坡稳定性评价[J].路基工程,2025,(5):37-44,8.

基金项目

新疆建设兵团财政科技计划重点研发项目(2022AB019) (2022AB019)