山地风电钢—混混合塔筒吊装施工技术

王耳东 蒲敏 常国武

云南水力发电2025,Vol.41Issue(10):84-86,154,4.
云南水力发电2025,Vol.41Issue(10):84-86,154,4.DOI:10.3969/j.issn.1006-3951.2025.10.022

山地风电钢—混混合塔筒吊装施工技术

Construction Technology for Hoisting Steel-Concrete Combined Tower Tube of Wind Powerplant in Mountainous Area

王耳东 1蒲敏 1常国武2

作者信息

  • 1. 中国水利水电第十四工程局有限公司,云南 昆明 650200
  • 2. 昆明智起吊装设备租赁有限公司,云南 昆明 650000
  • 折叠

摘要

Abstract

Combined with a wind power project in the Yunnan-Guizhou Plateau,this paper analyzes the construction requirements of the crane selection,lifting method,plane layout,ring piece assembly,tower verticality and concentricity control for the mixed tower lifting construction of wind power projects in mountainous complex terrain conditions.This paper elaborates on the consideration of terrain and tower parameters in the selection of cranes and lifting methods,and adopts a combined lifting method to refine the lifting parameters and layout requirements.It proposes a method for controlling the assembly accuracy of prefabricated rings and adjusting the verticality and concentricity control during the lifting process of the entire tower,which solves the problems of limited mountain transportation,environmental constraints,and high lifting process requirements for wind turbines.

关键词

山地/混凝土塔筒/吊装/预制混凝土管片/转换段/操作平台

Key words

mountainous area/concrete tower/lifting and hoisting/prefabricated concrete pipe segment/conversion section/operating platform