北京水务Issue(5):80-84,5.DOI:10.19671/j.1673-4637.2025.05.014
地下排桩技术在永定河山峡段村庄防护方案设计中的应用
Application of underground pile displacement technology in design of village protection program for Yongding River Mountain Section
高泽超 1张育辉 1马慧娟 1石文1
作者信息
- 1. 北京市水利规划设计研究院 北京 100048
- 折叠
摘要
Abstract
Aiming at the issue that the damage proportion of traditional bank protection reached as high as 78%in Shuiyuzui Village of the mountain section of the Yongding River after the"23·7"flood,a composite structure of"bored cast-in-situ piles+cantilever retaining wall"was constructed to improve the anti-scour capacity and adapt to the limited space conditions.Based on the 20-year return period flood discharge of 2 740 m3/s,the maximum scour depth was calculated to be 4.3 m.Combined with code verification and tool software checking,the pile length was determined to be 16 m with an embedded depth of ≥ 11.7 m,and reinforced gabions were adopted for protection.The results showed that the anti-scour flow velocity of the structure reached more than 5.0-8.0 m/s.The overall stability safety factor was 1.902,the anti-sliding factor was 1.986,and the embedded depth factor was 2.918.All these indicators met the code requirements.This composite structure provided a feasible technical path for the protection of mountain rivers in limited space.关键词
钻孔灌注桩/悬臂挡墙/钢筋石笼/永定河Key words
bored piles/cantilevered retaining walls/rock-filled steel cage/Yongding River分类
建筑与水利引用本文复制引用
高泽超,张育辉,马慧娟,石文..地下排桩技术在永定河山峡段村庄防护方案设计中的应用[J].北京水务,2025,(5):80-84,5.