Abstract
The cofferdam project of the tail water outlet of the hydropower project in the V-shaped river valley area is facing challenges such as narrow terrain,rapid flow and complex geological conditions.Reasonable cof-ferdam selection is essential to ensure the progress,construction safety and engineering benefits.Combined with the example of cofferdam construction at the tailwater outlet of Yebatan Hydropower Project,this paper analyzes the advantages of different cofferdam structures under the terrain conditions of V-shaped river valley,and provides reference for the design and construction of cofferdam under similar terrain conditions.关键词
V形河谷/尾水出口/围堰选型/叶巴滩水电站Key words
V-shaped valley/tailwater outlet/cofferdam selection/Yebatan Hydropower Project分类
水利科学引用本文复制引用
钱尚过..V形河谷条件下叶巴滩水电站尾水出口围堰选型研究[J].四川水力发电,2025,44(5):17-20,4.