摘要

Abstract

Taking the raw rock working face of Xinjiang Dananhu No.2 Mine as the research object,the article adopts FLUENT 19.2 software to establish the three-dimensional flow field model of water injection and pre-wetting in the open-pit coal mine working face,and analyzes the effects of water injection composition,water injection flow rate and water injection pressure on the water injection and pre-wetting effect in the open-pit coal mine working face,and designs the validation test for raw rock dust the water injection and pre-wetting.The results show that the effect of dust suppressant solution water injection pre-wetting is better than that of water injection pre-wetting only;the optimal water injection flow rate is 6 m/s and the optimal water injection pressure is 4 MPa,respectively;and the results of water injection pre-wetting validation test of the raw rock dust coincide with the numerical simulation results.The study provides a theoretical basis for the realization of dust suppression by water injection and pre-wetting of raw rock in the working face of open-pit coal mines.

关键词

露天煤矿/工作面/粉尘/注水预湿/数值模拟

Key words

open-pit coal mines/working surface/dust/pre-wetting by water injection/numerical simulation

分类

矿业与冶金

引用本文复制引用

赵晓亮,李一德,谢伟..新疆大南湖二矿原岩注水预湿研究[J].露天采矿技术,2025,40(6):1-6,6.

基金项目

鄂尔多斯市科技突围"揭榜挂帅"重点资助项目(JBGS2024010) (JBGS2024010)

国家重点研发计划资助项目(2019YFC1803801) (2019YFC1803801)

辽宁省教育厅理工类科研资助项目(LJ232410147061) (LJ232410147061)

露天采矿技术

1671-9816

访问量0
|
下载量0
段落导航相关论文