Optimization analysis of bidding design scheme for the Caculo Cabaça hydropower Project in Angola

左秋平 1张雄2

作者信息

  • 1. 中能建国际建设集团有限公司,北京 100022
  • 2. 中国葛洲坝集团三峡建设工程有限公司,湖北 宜昌 443000
  • 折叠

摘要

Abstract

In EPC project bidding,the design scheme has a significant impact on both bid cost and project duration.Based on the actual bidding practice of the Caculo Cabaça Hydropower Project in Angola,this paper conducts an in-depth analysis of its preliminary design scheme and summarizes approaches for optimizing the employer's basic design during the bidding stage,thereby effectively reducing construction costs,and shortening the construction period.The findings of this study can provide reference and guidance for international enterprises participating in overseas EPC project bidding.

关键词

水电站/投标/初步设计方案/设计方案优化

Key words

hydropower station/bidding/preliminary design scheme/design scheme optimization