| 注册
首页|期刊导航|长江科学院院报|水库连通工程取水口水力特性研究

水库连通工程取水口水力特性研究

叶焰中 林勇华 后小霞 渠立光 韩松林

长江科学院院报2026,Vol.43Issue(1):210-217,8.
长江科学院院报2026,Vol.43Issue(1):210-217,8.DOI:10.11988/ckyyb.20250487

水库连通工程取水口水力特性研究

Hydraulic Characteristics of Water Intakes in Reservoir Connection Project

叶焰中 1林勇华 1后小霞 2渠立光 2韩松林2

作者信息

  • 1. 深圳市原水有限公司,广东 深圳 518000
  • 2. 长江科学院水力学研究所,武汉 430010||水利部长江中下游河湖治理与防洪重点实验室,武汉 430010
  • 折叠

摘要

Abstract

[Objective]Water intake structures of reservoir connection projects are characterized by large water lev-el fluctuations,bidirectional flow,and operating modes affected by pipeline roughness,leading to a relatively com-plex hydraulic regulation process.Poor intake design or unreasonable regulation can easily cause a series of prob-lems.To analyze the key hydraulic issues of water intake structures in reservoir connection projects,this study took the Gongming-Qinglinjing Reservoir Connection Project as the research object.The hydraulic characteristics of bidi-rectional water intake and layered control intake were systematically investigated,and key issues and corresponding measures that needed to be focused on in the design of various types of water intakes were proposed.[Methods]Firstly,the hydraulic calculation method was used to analyze the hydraulic characteristics of the main conveyance line under different operating conditions and to assess the impact of roughness variation on flow conveyance capacity and water intake operating conditions.On this basis,hydraulic model tests were conducted to examine the flow pat-terns and local hydraulic characteristics of the bidirectional water intake and layered control intake under typical scheduling conditions.Finally,regarding the transitions between free surface and pressurized flow as well as closed hydraulic jump in the connecting tunnel behind the gate of the layered control intake,optimization recommendations were proposed from the perspectives of engineering measures and operational scheduling.[Results](1)the selec-tion of roughness had an important impact on the project's water conveyance capacity,water intake hydraulic char-acteristics,and project hydraulic scheduling.When the roughness increased from 0.011 to 0.016,the pipeline head loss increased by 108.2%-111.6%.Under maximum roughness conditions,the water conveyance capacity of the project must be ensured,while under small roughness conditions,particular attention must be given to the flow con-nection characteristics at the water intake.(2)Under inflow conditions,at bidirectional water intakes,the water surface in the reservoir area and the diversion channel was stable,the flow velocity was relatively small.After ente-ring the intake tower,the flow velocity increased,with no adverse flow patterns such as vortices or recirculation.Under outflow conditions,the flow at the water intake was smooth.The main flow increased in velocity after entering the diversion channel from the forebay,generating symmetrical recirculation on both sides.(3)During gate-con-trolled discharge,the layered control intake exhibited a free jet flow pattern.The jet impacted the wall of the energy dissipation well,fell to the bottom,and then entered the connecting tunnel section in an open-channel flow state.Adverse flow patterns such as closed hydraulic jumps might occur in the connecting tunnel.(4)Regarding the issue of closed hydraulic jumps,feasible preventive measures were proposed from the perspectives of engineering solu-tions and operational scheduling.(5)Reservoir connection projects had complex operating conditions.After the project was commissioned,the actual roughness of the main tunnel should be inversely calculated based on monito-ring data,and the hydraulic control methods should be adjusted in a timely manner.The research findings can pro-vide references for the design and operational scheduling of water intakes in similar water diversion projects.

关键词

双向输水取水口/分层控流取水口/叠梁门/糙率/水力特性/封洞水跃

Key words

bidirectional water intake/layered control intake/stop log gate/roughness/hydraulic characteristics/closed hydraulic jump

分类

建筑与水利

引用本文复制引用

叶焰中,林勇华,后小霞,渠立光,韩松林..水库连通工程取水口水力特性研究[J].长江科学院院报,2026,43(1):210-217,8.

基金项目

中央级公益性科研院所基本科研业务费项目(CKSF20241019/SL) (CKSF20241019/SL)

长江科学院院报

1001-5485

访问量0
|
下载量0
段落导航相关论文