摘要

Abstract

A phase difference exists between the extreme values of the total horizontal wave force and the wave uplift force.From the perspective of structural stability,the phase difference influences the stability of the pile foundation baffle permeable breakwater.In view of this situation,physical model tests under irregular waves without overtopping were conducted.The results show that a phase difference exists between the extremes of the total horizontal wave force and the wave uplift force,and the two forces do not reach the extreme values at the same time.Compared to the extreme value,the wave uplift force at the time of the peak total horizontal wave force is reduced,and the total horizontal wave force is reduced at the time of the peak wave uplift force.The main influencing factors,including wave steepness,relative breakwater width,relative superelevation,and the relative water entry depths of the front and rear baffles,were comprehensively considered.Using multiple regression analysis,the reduction factors for the wave uplift force at the peak total horizontal wave force and for the total horizontal wave force at the peak wave uplift force were analyzed,and the calculation formula of reduction coefficient was provided.

关键词

透空式防波堤/不规则波/水平波浪总力/浮托力/相位差/折减系数

Key words

permeable breakwater/irregular wave/total horizontal wave force/wave uplift force/phase difference/reduction factor

分类

交通工程

引用本文复制引用

唐毅杰,孙大鹏,陈欣欣..桩基挡板透空式防波堤稳定性试验研究[J].水道港口,2025,46(6):832-839,8.

基金项目

国家自然科学基金委员会-山东省人民政府联合基金资助项目(U1706226) (U1706226)