中国农村水利水电Issue(1):162-167,6.DOI:10.12396/znsd.2501369
单站双向调水泵站改造前后能效分析
Comparative Analysis of Energy Efficiency before and after Renovation of a Bidirectional Water Transfer Pumping Station
摘要
Abstract
The Guanbu Pumping Station supplies water in two directions:to the Xiajiashan Pumping Station and to the Hexi Reservoir.The head difference between these directions forces the system to rely on valve throttling for flow distribution,causing energy losses exceeding 28%of the pump head and cavitation risks during low-water-level operation.To address these issues,the system was redesigned into two independent one-way pipelines equipped with variable-frequency drives for flexible regulation.An evaluation model was developed based on hydraulic characteristics and operational constraints to analyze energy efficiency and optimal scheduling before and after the retrofit.Results showed that efficiency toward Hexi remained nearly unchanged,whereas the Xiajiashan direction avoided throttling losses,improved energy efficiency by 2.7%~10.2%,and eliminated cavitation risks.The findings provide a valuable reference for energy-saving retrofits and operational optimization of similar pumping stations.关键词
调水工程/关埠泵站/离心泵机组/节能改造/能效分析Key words
water diversion project/Guanbu Pumping Station/centrifugal pump unit/energy-saving renovation/energy efficiency analysis分类
建筑与水利引用本文复制引用
梁善丁,周龙才,杨伟沛,林丽平,梁健麟..单站双向调水泵站改造前后能效分析[J].中国农村水利水电,2026,(1):162-167,6.基金项目
国家自然科学基金项目(U2243235). (U2243235)