| 注册
首页|期刊导航|电力勘测设计|变电站沉降监测技术应用与案例分析

变电站沉降监测技术应用与案例分析

伏明星 罗海军 王彬 张兰军

电力勘测设计Issue(2):43-49,7.
✕
电力勘测设计Issue(2):43-49,7.DOI:10.13500/j.dlkcsj.issn1671-9913.2026.02.007

变电站沉降监测技术应用与案例分析

Application and Case Analysis of Subsidence Monitoring Technology in Substations

伏明星 1罗海军 1王彬 1张兰军1

作者信息

  • 1. 中国能源建设集团甘肃省电力设计院有限公司,甘肃 兰州 730070
  • 折叠

摘要

Abstract

Focuses on the settlement hazards in the equipment foundations of the 66 kV equipment area at a 750 kV substation,which have emerged during long-term operation.Based on the trigonometric leveling measurement technology of total station and the technical requirements of the"Code for Deformation Measurement of Buildings",a systematic settlement monitoring network was established:relying on 9 highly stable reference points and 204 precisely arranged monitoring points,a closed-loop observation route design and indirect adjustment algorithm were adopted to accurately calculate multi-period monitoring data;through Surfer software,spatial modeling and multi-dimensional analysis were conducted,generating contour maps,shaded relief maps,etc.,quantitatively characterizing the spatial heterogeneity of the site settlement.A systematic settlement monitoring and analysis of the substation site and equipment foundation was carried out,identifying high-risk settlement areas,providing a scientific decision-making basis for the safe operation and maintenance of the substation throughout its life cycle.The related technical framework has reference value for the settlement prevention and control of ultra-high voltage transmission and transformation projects.

关键词

变电站/三角高程测量/沉降监测/间接平差

Key words

substation/trigonometric leveling/settlement monitoring/indirect adjustment

分类

能源科技

引用本文复制引用

伏明星,罗海军,王彬,张兰军..变电站沉降监测技术应用与案例分析[J].电力勘测设计,2026,(2):43-49,7.

电力勘测设计

1671-9913

访问量0
|
下载量0
段落导航相关论文