摘要
Abstract
This paper combines the daily management of the piezometers of the Beijiang Embankment and the practical experience of seepage monitoring during the flood period of the Beijiang River.With the help of the client of the Hydraulic Engineering Safety Intelligent Monitoring and Early Warning System(DSIMS5.0),it analyzes key technical issues such as the design of the data analysis section of the automated piezometers,the observation of the phreatic line,and the seepage pressure.By analyzing the monitoring data from a multi-dimensional perspective,this paper proposes technical methods for the application of key data,aiming to improve the accuracy and reliability of the monitoring data,and provides data support and theoretical basic materials for the analysis and research of the seepage safety of the embankment project.关键词
堤防/测压管/自动化监测/渗流量/数据分析Key words
embankment/piezometer/automated monitoring/seepage discharge/data analysis分类
建筑与水利