重载铁路港前站接卸系统能力研究

张永恒 石江 张进川 王敏

铁路物流2026,Vol.44Issue(3):32-39,8.
铁路物流2026,Vol.44Issue(3):32-39,8.DOI:10.16669/j.cnki.issn.2097-5899.202502260002

重载铁路港前站接卸系统能力研究

Capacity of Receiving and Unloading System in Heavy-Haul Railway Port Station

张永恒 1石江 2张进川 3王敏3

作者信息

  • 1. 中国神华能源股份有限公司 煤炭运输部,北京 100011
  • 2. 国能运输技术研究院有限责任公司 重载运输技术研究中心,北京 100080
  • 3. 北京交通大学 交通运输学院,北京 100044
  • 折叠

摘要

Abstract

To accurately assess the capacity of the receiving and unloading system in the heavy-haul railway port station,the research divided the system into three parts according to the technical operation process of the port station:the arrival subsystem,the transfer subsystem,and the unloading subsystem,which together constituted a three-stage tandem queuing system.The distribution law of the traffic flow and service flow in each subsystem was analyzed,and a queuing model was built using queuing theory.By studying the system capacity under the influence of unbalanced operating time and the interaction of the previous and next operating links,the parameters and queuing indicators of each subsystem were calculated.Finally,taking Shengang Station as an example,the parameters and indicators were determined using the proposed model.Its capacity was calculated and bottlenecks were analyzed.The research results provide a theoretical reference for the capacity optimization of the receiving and unloading system in the heavy-haul railway port station.

关键词

重载铁路/港前站/接卸系统/系统能力/排队论

Key words

Heavy-Haul Railway/Railway Port Station/Receiving and Unloading System/System Capacity/Queuing Theory