首页|期刊导航|四川水力发电|LJY水库工程埋藏式月牙肋岔管制造安装工艺探讨

LJY水库工程埋藏式月牙肋岔管制造安装工艺探讨

何攀 姜鹏

四川水力发电2026,Vol.45Issue(2):83-89,7.
四川水力发电2026,Vol.45Issue(2):83-89,7.DOI:10.20196/j.cnki.scslfd.20260218

LJY水库工程埋藏式月牙肋岔管制造安装工艺探讨

Discussion on manufacturing and installation technology of buried crescent ribbed bifurcated pipe in LJY Reservoir Project

何攀 1姜鹏2

作者信息

  • 1. 成都市李家岩开发有限公司,四川 成都 610213
  • 2. 四川能源发展集团有限责任公司,四川 成都 610213
  • 折叠

摘要

Abstract

8 crescent ribbed bifurcated pipes are arranged according to the geological conditions of the surround-ing rock in the urban and rural water supply tunnel diversion system to meet the functions of urban and rural water supply,irrigation,power generation of the LJY Reservoir Project.The paper the manufacturing and in-stallation technology control of the buried crescent rib bifurcated pipe at 0+159.43 m.The paper introduces the structural form and main features of the buried crescent ribbed bifurcated pipe in terms of manufacturing and installation,and further elaborates on the design of the buried crescent ribbed bifurcated pipe according to the actual situation.describes the preparation,cutting,winding,welding,pre-assembly and other manufacturing processes of the crescent ribbed bifurcated pipe and discusses the implementation of transportation,assembly,welding and quality inspection of bifurcated pipe in the chamber.Upon the completion of the bifurcated pipe's manufacturing and installation,vibration aging treatment and hydrostatic pressure testing were employed to assess the overall quality of the crescent-ribbed bifurcated pipe,and the effectiveness of these verification measures is analyzed herein.

关键词

埋藏式月牙肋岔管/振动时效工艺/制造工艺/安装工艺

Key words

buried crescent ribbed bifurcated pipe/vibration aging process/manufacturing process/installation technology

分类

建筑与水利

引用本文复制引用

何攀,姜鹏..LJY水库工程埋藏式月牙肋岔管制造安装工艺探讨[J].四川水力发电,2026,45(2):83-89,7.