摘要

Abstract

This paper addresses the challenge of structural deformation inherent in the large-scale and thin-walled characteristics of steel containment vessel(CV)cylindrical modules during nuclear island construction for nuclear power plants.It systematically introduces an integrated hoisting-transportation construction technique.The core of this technique lies in integrating the hoisting and transportation processes into a managed continuum through integrated process design,development of specialized tooling,and precise process control,with a primary focus on overcoming deformation control challenges for the massive cylindrical structure throughout then tire handling operation.The summarized key technical points and implementation experience provide crucial technical references and practical guidance for the safe,efficient,and high-quality execution of hoisting and transportation phases in subsequent large-scale,thin-walled modular projects of a similar nature.

关键词

核岛/CV筒体/吊装运输一体化/反应堆/模块化

Key words

nuclear island/containment vessel(CV)/integrated hoisting-transportation/reactor/modularity

分类

信息技术与安全科学

引用本文复制引用

李富军..核岛CV筒体模块吊装运输一体化施工技术研究与应用[J].科技创新与应用,2026,16(13):14-17,4.

科技创新与应用

2095-2945

访问量1
|
下载量0
段落导航相关论文