云南水力发电2026,Vol.42Issue(6):85-89,5.DOI:10.3969/j.issn.1006-3951.2025.12.021
内悬浮内拉线抱杆分解组立铁塔施工技术
Construction Technology of Decomposing and Assembling Iron Towers with Inner Suspension and Inner Cable Holding Pole
石正鹏 1刘香仙1
作者信息
- 1. 中国水利水电第十四工程局有限公司,云南 昆明 650200
- 折叠
摘要
Abstract
With the continuous growth of demand for renewable energy worldwide,photovoltaic power generation,as a key area of green energy,has also seen an increase in construction volume and process standards.In this context,the construction technology of decomposing and assembling iron towers with internal suspension and internal cable holding poles has been widely adopted in photovoltaic project construction due to its high efficiency and safety.This paper will conduct in-depth research on the construction process of decomposing and assembling iron towers with internal suspension poles,exploring their technical characteristics,force analysis,construction process,and application effects.关键词
光伏项目/内悬浮抱杆/分解组立/铁塔施工/受力分析Key words
photovoltaic project/internal suspension pole/decompose and assemble/tower construction/force analysis分类
信息技术与安全科学引用本文复制引用
石正鹏,刘香仙..内悬浮内拉线抱杆分解组立铁塔施工技术[J].云南水力发电,2026,42(6):85-89,5.