| 注册
首页|期刊导航|山东煤炭科技|煤柱下高应力区面向采空区贯通方案优化与应用

煤柱下高应力区面向采空区贯通方案优化与应用

赵现平

山东煤炭科技2026,Vol.44Issue(6):7-14,8.
✕
山东煤炭科技2026,Vol.44Issue(6):7-14,8.DOI:10.3969/j.issn.1005-2801.2026.06.002

煤柱下高应力区面向采空区贯通方案优化与应用

Optimization and Application for Goaf Penetration Scheme in High Stress Zone Under Coal Pillars

赵现平1

作者信息

  • 1. 兖矿能源集团股份有限公司济宁三号煤矿,山东 济宁 272100
  • 折叠

摘要

Abstract

The mining activities have led to the penetration of interconnected roadways in the remaining coal pillars into the goaf,causing stress superposition effect and forming high stress concentration zones.Conventional pressure relief ways are difficult to eliminate large-energy rock burst events.Aiming at this problem,based on the limit equilibrium theory,a fully plastic pressure relief scheme for the roof is proposed:the ultimate stress around the roadway is released through roof drilling,forming a fracture zone around the hole(blocking the accumulation of elastic energy),and a spherical crack network is constructed by combining roof blasting.The on-site application results indicate that the maximum microseismic energy is decreased from 1.16×104 J to 4.38×103 J,with a decrease of 62.3%;But the fissures at 15-25 m of the remaining penetration section are not penetrated,with significant stress concentration.The conclusion shows that the roof full plastic pressure relief scheme can effectively reduce the impact risk,and the width of the pressure relief protection zone should not be less than 15 m,providing a technical reference for the penetration problem in similar high stress zone.

关键词

煤柱/高应力区/顶帮全塑性卸压/采空区贯通/微震监测

Key words

coal pillar/high stress zone/roof and side full plastic pressure relief/goaf penetration/microseismic monitoring

分类

矿业与冶金

引用本文复制引用

赵现平..煤柱下高应力区面向采空区贯通方案优化与应用[J].山东煤炭科技,2026,44(6):7-14,8.

山东煤炭科技

1005-2801

访问量0
|