近距煤层滞后充填开采覆岩运移特征研究

李刚 吕晓磊 郭泽周

山东煤炭科技2026,Vol.44Issue(6):48-55,8.
✕
山东煤炭科技2026,Vol.44Issue(6):48-55,8.DOI:10.3969/j.issn.1005-2801.2026.06.008

近距煤层滞后充填开采覆岩运移特征研究

Research on Overburden Rock Migration Characteristics of Delayed Filling Mining in Close Distance Coal Seam

李刚 1吕晓磊 1郭泽周2

作者信息

  • 1. 国网能源哈密煤电有限公司,新疆 哈密 839000
  • 2. 中国矿业大学矿业工程学院,江苏 徐州 221116||新疆工程学院矿业工程与地质学院,新疆 乌鲁木齐 830023||新疆煤炭资源绿色开采教育部重点实验室(新疆工程学院),新疆 乌鲁木齐 830023
  • 折叠

摘要

Abstract

In order to explore the influence law of close distance coal seam mining on overburden rock stress and displacement development,and effectively prevent disasters such as roof fall and caving,rock burst and others caused by close distance coal seam mining in coal production,taking Dananhu No.1 Mine in Hami as an example,through methods of theoretical analysis and numerical simulation,the overburden rock migration characteristics in close distance coal seam mining are explored.The results show that the lower coal seam mining at close distance coal seams exacerbates the stress concentration and displacement deformation of the overburden rock,directly increasing the roof safety hidden dangers caused by close distance coal seam mining.Therefore,a delayed filling mining method for the upper coal seam is proposed,which can effectively alleviate the impacts caused by stress concentration and displacement deformation of the overburden rock,and achieve relatively effective control.

关键词

近距煤层/覆岩/运移/规律

Key words

close distance coal seam/overburden rock/migration/law