四川水力发电2026,Vol.45Issue(z1):142-145,4.DOI:10.20196/j.cnki.scslfd.2026S129
东西关船闸人字门底枢更换施工技术
Replacement construction technology for the bottom pivot of the miter gate at Dongxiguan Ship Lock
许可 1苏小明 1田文恒1
作者信息
- 1. 中国水利水电第十工程局有限公司,四川 都江堰 611833
- 折叠
摘要
Abstract
As an important navigation structure in the Jialing River Basin,the Dongxiguan Ship Lock have been suffering from severe abrasion on their bottom hinge of the miter gates due to long-term exposure to alterna-ting heavy loads and friction.Therefore,the bottom hinge needs to be replaced.This paper addresses technical difficulties of replacing the bottom hinge from three aspects:the lifting scheme,the control of the reinstallation accuracy of the bottom hinge,and the disassembly and assembly technology.Based on the maintenance experi-ence of the Three Gorges and other ship locks,a construction plan combining a low-position synchronous lifting system with a precision measurement control network is proposed.The research shows that a rational lifting process and precise positioning technology are the core to ensuring the quality of the bottom hinge replace-ment.The results of this paper can provide technical references for the replacement of the bottom hinge of mi-ter gates in similar projects.关键词
东西关船闸/人字门/底枢更换/顶升工艺Key words
Dongxiguan Ship Lock/miter gate/bottom pivot replacement/lifting technology分类
交通工程引用本文复制引用
许可,苏小明,田文恒..东西关船闸人字门底枢更换施工技术[J].四川水力发电,2026,45(z1):142-145,4.