Abstract

Yingliangbao Hydropower Station with a typical long-diversion layout,is a key 13th Five-Year Plan project.This paper presents its primary electrical design,including grid connection,main electrical wiring,aux-iliary power,major electrical equipment,grounding and lighting.New technologies and materials such as three-phase integrated shunt reactor and basalt-fiber cable trays are used.Operational results show that the scheme is safe and stable,which provides references of the green and low-carbon construction for similar projects.

关键词

长引水式水电站/电气一次设计/三相一体电抗器/玄武岩纤维桥架

Key words

long diversion-type hydropower station/primary electrical design/three-phase shunt integrated reac-tor/basalt fiber cable tray

分类

农业科技

引用本文复制引用

钟沛,于青坤,陈九林,李超凡,屈柏林..硬梁包水电站电气一次设计[J].四川水力发电,2026,45(4):125-130,6.