中国水利Issue(18):61-70,10.DOI:10.3969/j.issn.1000-1123.2026.18.007
基于二维水动力模型的溃坝洪水模拟研究
Simulation of dam-break flooding based on a two-dimensional hydrodynamic model:a case study of Huoshishan Reservoir in Biyang County,Zhumadian City,Henan Province
摘要
Abstract
In view of the abrupt onset and high destructive power of floods following dam failure,clarifying the propagation and inundation patterns of dam-break floods is an important basis for disaster prevention and mitigation and for formulating emergency evacuation plans.Taking the Huoshishan Reservoir in Biyang County,Zhumadian City,Henan Province,as the study object,a GPU-accelerated two-dimensional hydrodynamic model was constructed and coupled with a gradual dam-break calculation model to simulate the progressive expansion of the breach.The dam-break outflow was superimposed on the spillway discharge to form the inflow boundary.Three scenarios—the design flood,the check flood,and the flood exceeding the dam crest elevation—were selected to simulate the routing of dam-break floods in the downstream plain area,and the inundation extent,water depth distribution,and flood-peak propagation characteristics were quantitatively analyzed.The results show that under the scenario of the flood exceeding the dam crest elevation,the dam-break flood exhibits a pattern of"rapid rise—single peak—gradual recession",and the inundation depth undergoes a dynamic evolution of"shallow-water overbank spreading—increasing water depth—deep-water dominance—slow recession of shallow water".The spillway pre-release and the gradual breaching mode of the earth-rockfill dam can reduce the dam-break flood peak.As the flood propagates downstream,the onset of rise and peak occurrence are successively delayed,the peak attenuates along the routing path,and the inundation duration shortens.Jiuligang Village in Chunshui Town,located closest to the dam,experiences the greatest inundation depth and the longest inundation duration,and thus has the highest risk.As the upstream inflow condition escalates from the design flood to the flood exceeding the dam crest,the downstream inundation area increases from 2.86 to 7.76 km2,the maximum inundation depth rises from 6.67 to 10.65 m,and the proportion of deep-water areas with water depths greater than 3.0 m increases from 6.3%to 30.9%,indicating progressively increasing hazard severity.关键词
溃坝洪水模拟/逐渐溃坝计算模型/二维水动力模型/洪水模拟/淹没分析/火石山水库Key words
dam-break flood simulation/gradual dam-break calculation model/two-dimensional hydrodynamic model/flood simulation/inundation analysis/Huoshishan Reservoir分类
建筑与水利引用本文复制引用
王韫策,冷艳杰,臧文斌,孙伊博,刘世昆,阚光远..基于二维水动力模型的溃坝洪水模拟研究[J].中国水利,2026,(18):61-70,10.基金项目
国家重点研发计划项目(2023YFC3209202). (2023YFC3209202)