摘要

Abstract

The source-grid-load-storage integrated project effectively promotes the local consumption of clean energy by integrating resources of generation sources,power grid,load,and energy storage.Its grid-connected operation relies on reserve services provided by the public power grid.However,there is a contradiction between the reserve demand based on the total system load and the current allocation mechanism based on the net load of entities,which fails to adequately reflect the actual occupation situation of system reserve resources,leading to cost shifting and market fairness issues.Therefore,the underpayment of reserve cost for source-grid-load-storage integrated projects resulting from the flaws in the current allocation mechanism is firstly analyzed,and an improved reserve cost allocation method for source-grid-load-storage integrated projects is proposed to enhance fairness.Secondly,a mathematical model for an analytical framework is developed to realize the comparison and verification between current mechanisms and the proposed method.Finally,sensitivity analysis is carried out for the influencing factors,including the scale of the source-grid-load-storage integrated projects,the internal renewable energy proportion,and the ratio of wind power to photovoltaic.The case study results reveal the flaws of current mechanisms and verify the effectiveness of the proposed allocation method.

关键词

源网荷储/备用成本/成本分摊/公平性

Key words

source-grid-load-storage/reserve cost/cost allocation/fairness

引用本文复制引用

王雨萱,于松泰,刘硕,雍培,余娟,杨知方..面向公平性提升的源网荷储一体化项目备用成本分摊方法[J].电力系统自动化,2026,50(20):202-213,12.

基金项目

北京电力交易中心有限公司科技项目(SGJY0000YJJS2400048) (SGJY0000YJJS2400048)

国家自然科学基金资助项目(52407081). This work is supported by Beijing Electric Power Trading Center Co.,Ltd.(No.SGJY0000YJJS2400048)and National Natural Science Foundation of China(No.52407081). (52407081)