摘要

Abstract

To address the challenges in quantifying transient rotor angle security boundaries and incorporating transient stability constraints into new power system energy storage planning,this paper proposes a data-driven paradigm for constructing rotor angle transient stability security constraints and a framework for embedding such constraints into energy storage capacity planning.Firstly,a combined'mechanism simulation-black-box mapping'strategy is employed to establish a fast transient-stability labeling mechanism and to generate a large-scale,validated data set.Secondly,an interpretative modeling approach based on'mutual information-decision tree'is applied to identify key controllable state variables and derive an explicit formulation of the transient rotor angle security region.These transient security constraints are then embedded into a zonal power system operation model,resulting in a bi-level optimization framework that integrates capacity planning with zonal operation.Finally,simulations are carried out on a three-zone test system using the PSD Power Tools and actual grid planning data.Experimental results show that the proposed data-driven transient stability constraints effectively characterize the transient security boundaries of zonal systems and provide accurate safe operation intervals for controllable coupling variables.Moreover,the bi-level planning model with embedded transient security constraints successfully balances the economic investment in energy storage with the efficiency of renewable energy integration,while ensuring the transient stability of the system rotor angles.This significantly enhances the feasibility and practical applicability of the planning scheme.

关键词

储能容量规划/暂态功角安全约束/数据驱动/暂稳安全域刻画/分区规划

Key words

energy storage capacity planning/transient rotor angle stability constraints/data-driven/transient stability security domain characterization/zone planning

分类

信息技术与安全科学

引用本文复制引用

高正男,王铁柱,郭剑波,马士聪,单熙雯,侯玮琳..计及暂态功角安全约束的电力系统储能分区容量规划方法[J].电网技术,2026,50(10):3996-4005,中插17-中插21,15.

基金项目

智能电网重大专项(2030)资助项目(2025ZD0805100) (2030)

国家电网有限公司科技项目(SGNXJY00ZWJS2500096).Project Supported by Smart Grid-National Science and Technology Major Project(2025ZD0805100) (SGNXJY00ZWJS2500096)

Science and Technology Project of State Grid Corporation of China(SGNXJY00ZWJS2500096). (SGNXJY00ZWJS2500096)