郑州轻工业学院学报(自然科学版)2012,Vol.27Issue(4):98-101,4.DOI:10.3969/j.issn.1004-1478.2012.04.025
基于贝叶斯网络的电力工程项目延迟风险研究
Research on schedule risk in power construction project using Bayesian network
摘要
Abstract
Schedule risk factors of power projects are quantified by Baysian networks (BN) model. Results showed that five kinds of risk factors such as poor weather conditions, tight project schedule, low-skilled jobs,lack of equipment and not timely supplier will directly impact on project schedule. Factors including not timely supplier,low technical work ability,improper plan arrangement are sensitive to project schedule, which should be the focus of control.关键词
贝叶斯网络/延迟风险/电力工程项目Key words
Bayesian network/ schedule risk/ power construction project引用本文复制引用