为准确模拟堰塞坝的形成过程,在物质点方法中引入了滑动速度依赖型的摩擦系数模型,实现了滑面接触算法的求解,并与试验结果对比验证方法的可靠性.在此基础上,反演了白格滑坡堰塞坝的形成过程,探讨了滑床底摩擦对堰塞坝成坝模式的影响规律.研究结果表明:白格滑坡堰塞坝形成过程可分为滑坡体加速运动、河谷制动和堆积成坝三阶段.白格滑坡速度最大达到45m/s且最大速度位于滑坡体后缘,而滑坡体前缘受到河床底部摩擦影响,速度不稳定,变化幅度大且比滑坡体后缘早20s制动.不同滑面接触模式决定了滑坡最终堆积成坝的状态:若采用滑动速度依赖型的摩擦系数模型模拟,则能够真实反映白格滑坡堰塞坝堆积状态;采用滑面的峰值摩擦系数计算,则导致计算的白格滑坡运动距离减小了32%,不能形成完全堵塞金沙江的堰塞坝;而采用残余摩擦系数计算,则导致计算的白格滑坡运动距离增大了12%.研究成果对加深堰塞坝成坝模式的认识具有意义,对于滑坡堰塞坝链生灾害预测及防灾减灾应急抢险处置具有一定的参考价值.

In recent years,frequent seismic activities and extreme weather conditions have induced numerous landslide barrier dams,posing a severe threat to the lives,property,and infrastructure of river basins.In this paper,a friction coefficient model de-pendent on sliding velocity was introduced into the material point method to solve the sliding surface contact algorithm.The im-proved method's reliability was validated by comparing it with experimental results.Based on this,the inverse analysis for the for-mation process of the Baige landslide barrier dam was carried out,and the influence of sliding bed friction on the damming mode of the landslide dam was discussed.The research results indicated that the formation process of the Baige barrier dam can be di-vided into three stages:accelerated movement,braking in valley,and dam accumulation of the landslide mass.The maximum ve-locity of the Baige landslide reached 45 m/s,with the highest velocity located at the rear of the landslide mass.The front of the landslide mass was influenced by bed friction,resulting in unstable velocity and significant fluctuations,and a 20-second earlier stoppage compared to the landslide mass's rear.Different contact models for the sliding surface determine the final damming state of the landslide.Simulating with a friction coefficient model dependent on sliding velocity accurately reflects the accumulation state of the Baige landslide dam.While using the peak friction coefficient of the sliding surface,the movement distance of the Baige landslide reduced by32%,and it prevents the complete blockage of the Jinsha River by the dam.While calculating with the residual friction coefficient,the movement distance increased by12%.The research findings are of significant importance in deep-ening our understanding of the damming mode of landslide dams.They provide valuable references for disaster prediction,mitiga-tion,emergency response,and geological disposal in landslide dam chain disasters.

钟启明;吴昊;单熠博;赵鲲鹏

南京水利科学研究院,江苏 南京 210024||水利部水库大坝安全重点实验室,江苏 南京 210024南京水利科学研究院,江苏 南京 210024

水利科学

物质点法数值模拟接触模型摩擦系数白格滑坡堰塞坝

material point methodnumerical simulationcontact modelfriction coefficientBaige landslide barrier dam

《人民长江》 2024 (004)

25-31,43 / 8

国家自然科学基金区域创新发展联合基金重点支持项目(U22A20602);国家自然科学基金青年基金项目(42207228)

10.16232/j.cnki.1001-4179.2024.04.004